Mill & Overlay Projects

Post Date:08/08/2018

Grand Forks, ND – With the Mill & Overlay nearing completion on Washington St., the contractor has their schedule for the remaining Mill & Overlay projects around Grand Forks.  A Mill & Overlay project consists of removing the existing surface of the road (mill) and placing a new surface on the road (overlay).

Wednesday, Aug. 8-9, 2018
Mill N. 20th St. (University Ave. to Gateway Dr.)

Friday, Aug. 10, 2018

Mill Belmont Road (Park Dr. to 32nd Ave. S.)

Mill 27th Ave. S. (S. 20th St. to 28th Ave. S.)

Pave N. 20th St. (University Ave. to Gateway Dr.)

Monday, Aug. 13, 2018

Mill S. 20th St. (24th Ave. S. to 32nd Ave. S.)

Mill 17th Ave. S. (Washington St. to S. 12th St.)

Pave Belmont Road (Park Dr. to 32nd Ave. S. access to Lincoln Golf Course will be from the North)

Pave S. 20th St. (24th Ave. to 32nd Ave. S.)

Pave 27th Ave. S. (S. 20th St. to 28th Ave. S.)

Pave S 19th St (25th Ave S to 27th Ave S)

Pave 25th Ave S (S 20th St to S 19th St)

Tuesday, Aug. 14, 2018

Mill Cherry St. (4th Ave. S. to 11th Ave. S.)

Pave 62nd Ave. (Belmont Road to Washington St.)

Pave 17th Ave. S. (Washington St. to S. 12th St.)

Pave Adams Dr. (Desiree Dr. to 62nd Ave. S.)

Wednesday, Aug. 15, 2018

Pave Adams Dr. (Desiree Dr. to 62nd Ave. S.)

Thursday, Aug. 16, 2018

Pave Cherry St. (4th Ave. S. to 11th Ave. S.)

This schedule is tentative as there may be changes due to weather or mechanical breakdown.