Below is an interactive map showing City infrastructure projects such as sewer, water, paving, street lights, etc. 

For information about building construction on private property, click here.

Interactive Construction Projects Map Click Here

 

Interactive Project Detour Map Click Here

 

Project  Project Description  Start  Date End  Date
7164

Demers Avenue (I-29 to Fire Station) & Shared Use Path (48th to 42nd St)

Pavement repairs, catch basin repairs

Traffic signal upgrades

Present: Contractor working on Columbia Road to Fire Station inside lanes, doing repairs and night work at intersection. Pavement grading end of month.

Contractor: Interstate Improvement, Faurbault, MN $4.9M

4/10/17 9/23/17
7024

Kennedy Bridge Rehabilitation

Replace west abutment, all concrete deck/roadway, structure painting

Traffic reduced to one lane in each direction. Bridge to be closed tor 3 days twice each year during paving operations.

Present:Traffic lanes moved to the north half of the bridge.Bridge raised onto temporary pier. Pile driving for replacement pier 6/16/17-6/23/17. Bridge to be lowered onto replacement pier week 2 August. The removal of bridge deck on south side completed.

Click here to access the website for the project

Contractor: Zenith Tech Inc, Waukesha, WI $15.6M

4/3/17 10/15/17
7143

Reconstruction of Columbia Rd (40th-47th AS)

Construct 4 lane divided highway from south of 40th Ave S through intersection at 47th Ave S. A traffic signal and turn lanes will be constructed at 47th Ave S.

The roadway between the two intersections will be closed until completed. The intersection at 47th Ave S. will be closed for a 30 day period between July 8 and August 19 to allow for 2 lanes to be completed and intersection opened.

 

Contractor: Reede Construction, Aberdeen, SD $4.5M

5/8/17 9/15/17
7634

Bridge Deck Overlay at University/I-29

Top few inches of deck milled off and failed spots of deck below this level being patched. Work underway to repair railing on south side of bridge. New concrete surface to be poured. Curb/rail on south side to be repaired due to damage from I-29 over-height load. One lane of traffic to be open during construction and will be controlled by temporary signals.

Contractor: Industrial Builders, Inc.

 5/31/16 8/26/17 

 