Site Plan Review

Print
Press Enter to show all options, press Tab go to next option

 

ENGINEERING SITE PLAN REVIEW

 SITE PLAN    1ST REVIEW 2ND REVIEW 3RD REVIEW FINAL APPROVAL 
 Truyu  Received  11/14/2017      11/16/2017
 Completed  11/16/2017    
   In Bluebeam    
 
Wells Concrete  Received  10/24/2017  11/13/2017  11/20/2017 11/20/2017 
Completed  10/27/2017  11/16/2017 11/20/2017 
  Comments  In Bluebeam   
 
 Altru South Campus
Parking Lot
 Received 10/20/2017      10/20/2017 
 Completed 10/20/2017     
       
 
 Office at 624 8th Ave N  Received 10/10/2017  11/3/2017  11/29/2017  11/30/2017 
 Completed 10/12/2017  11/7/2017  11/30/2017 
   Comments In Bluebeam   
 
 Simplot Freezer  Received  9/27/2017     9/29/2017 
 Completed  9/29/2017    
   Comments    
 
 Goldmark
615 6th Ave N
 Received 9/27/2017       9/29/2017
 Completed 9/29/2017     
   Comments    
 

 FedEx
2700 N. Washington St.

 Received    9/15/2017   10/2/2017 
 Completed    9/21/2017  
       
 
 Community Contractors  Received  9/21/2017      9/21/2017
 Completed  9/21/2017    
       
 
   Received        
 Completed