Mill & Overlay Projects Tentative Schedule

Post Date:06/02/2026

Grand Forks, ND – Crews will be doing several Mill & Overlay jobs throughout the city over the next several weeks.  Mill & Overlay projects consist of crews grinding down the existing road surface (Milling) and overlaying a new surface (Overlay).

Here is the Mill & Overlay tentative schedule:

62nd Ave S (S. Columbia Rd. – S. Washington St.)

6/2-6/4

 

S 4th St. (Kittson Ave. – Gertrude Ave.)

Division Ave., Bruce Ave. Gertrude Ave. (3rd St. – 5th St.)

6/15-6/17 after 5 pm everyday

Road will be open with parking from 8am-5pm every day.

 

17th Ave S (Cherry St. – Belmont Rd.) 

6/22-6/23

 

S 26th St (24th Ave. S. – 28th Ave. S.)

26th Ave. S. (S. Columbia Rd. – S. 25th St.)

6/29-6/30

 

This schedule may change due to weather or contractor availability.  Crews are required to give 48 hr. notice to residents impacted by work in their area.